“Mary’s Crown” Time Lapse

Here’s a time lapse video of “Mary’s Crown” (the compression ring) and the associated roof supports being put in place.

YouTube Preview Image

“Mary’s Crown” and the roof beams go up

The day started off with a beautiful “God moment” as “Mary’s crown” (the compression ring to which all of the roof beams connect) was raised into the sky by a crane as the sun rose to the east.

20120516-224720.jpg

From there, the roof beams were raised one by one, put into place and attached to the existing steel framework of the church and the compression ring.

20120516-224837.jpg
The first three beams are in place.

20120516-224944.jpg
Four beams now in place.

20120516-225043.jpg
Six beams now in place.

20120516-225147.jpg
This view shows the new bell tower very clearly.

20120516-225334.jpg
The seventh beam being raised up into position.

20120516-225422.jpg
This close up shows exactly how the beams fit into the compression ring at the top of the roof.

20120516-225534.jpg
The seventh beam is now in place with one left to go.

20120516-231007.jpg
All eight beams now in place.

Bell Tower Time Lapse 05-07-12

Here’s a time lapse video of the bell tower going up, taken on May 7th.

YouTube Preview Image

Construction Update 04-28-12

Interior walls in the lower level are being put in place. The photo below shows an interior wall for the lower level restroom.

20120516-111807.jpg

Foundation Concrete Pour

The pour of the concrete foundation took place on Monday. The first picture shows the pour in action, the next two show the end results.

20120424-080701.jpg

20120424-080718.jpg

20120424-080737.jpg

Knights of Columbus donation

The Knights of Columbus presented a check to Fr. Carl for $30,000 last night to go toward the new church. Thanks to the Knights for all the service they provide to our parish.

20120421-090604.jpg

Parishioner Rocks Placed in Foundation

Our personalized rocks were spread in the lower level of the church today directly under where the altar will be on the main level. The foundation pour is scheduled for this coming Friday which will make these rocks part of the physical foundation of the new building.

20120417-225404.jpg

20120417-225422.jpg

20120417-225443.jpg

Construction Update 04-16-12

A picture of the concrete pour for the first floor slab on metal deck.

20120416-222734.jpg

Construction Update 04-05-12

Here is a view from the south staircase looking at front of church.

20120416-222228.jpg

This picture is a view of the sanctuary space from Baptismal Font location. Metal deck placement is nearing completion and crews are preparing for the placement of the concrete on the first floor.

20120416-222425.jpg

Construction Update 04-03-12

Here is a picture of current progress taken from south of the church.

20120404-212214.jpg